Construction of the Tres Rios Full Scale Project levees and emergent wetlands has been completed. Refer to the schedule below for the individual phases and their start and completion dates.
Schedule:
| Phase |
Tentative Start |
Tentative End |
| 1A (levee 105th to Avondale Blvd.) |
----------------- |
Completed 5/2007 |
|
|
|
| 1B (levee Avondale Blvd. to the Agua Fria
River) |
----------------- |
Completed 6/2008 |
|
|
|
| 2A (Effluent Pump Station) |
7/2009 |
7/2012 |
|
|
|
| 2B (Emergent Wetlands) |
12/2009 |
5/2010 |
| 3 (Riparian and open water in river) |
7/2010 |
7/2013 |
|
|
|
|
|
|