Menu
* What's New
* Project Benefits
* Construction Activities and Schedule
* Project Map
* Project Photos
* Public Communications
* Keeping You Informed

Broadway Road Sewer Main Replacement Project

The following also is provided in Spanish. Lo siguiente también es provisto en Español.

Segment 2C

Construction to install the 30" sewer main will begin between 7th and Central Avenues the week of October 17. The 12" water main is currently being installed between 14th and 17th Streets. The sewer main pipe will go under the 7th and Central Avenue intersections (with no open trench through the intersections).

Please drive carefully through the construcion zones.

Segment 2B

Complete

Segment 2A

Complete



Last modified on 10/13/2011 21:57:27