​Description

Street reconstruction project to widen and re-pave the roadway, upgrade street lights and signals to new city standards, repair sidewalks and add a new storm drain to improve roadway drainage and reduce street flooding.

Project Highlights

  • Widen roadway to add a two-way left turn lane
  • New pavement
  • Sidewalk repairs
  • Street light upgrades
  • Traffic signal improvements
  • New storm drain

Goals of the Project

  • Improve traffic flow by providing a dual left turn lane for commercial vehicles to access properties in this industrial area
  • Improve the roadway surface
  • Improve pedestrian safety and connectivity
  • Improve drainage
  • Improve street lighting and signals

Schedule

​Final Design and Right of Way Acquisition - Anticipated to be completed by May 2022

Construction - Anticipated to begin by the end of 2023


Project Contact

Michael A. Cano
(602) 262-4054
michael.cano@phoenix.gov​


 

Updated November 2022