​​​T2050 Logo

​Description

Phoenix has grown through the years and different parts of the city have different characteristics. Numerous neighborhoods lack sidewalks, paths, upgraded ramps for people with disabilities and other amenities that make moving around the city safer and easier. When working on street improvement projects, the city is required to update any existing curb ramps to the latest Americans with Disabilities Act (ADA) standards. This page will help you learn about mobility area and sidewalk projects that are planned, under construction or recently completed. 

Mobility and safety is at the heart of what we do with all of our street transportation projects. This page is not inclusive of all projects intended to address mobility issues. For a full list of major projects, visit phoenix.gov/streets/projects​.​


​Central Avenue, Alta Vista Road to 7th Street

This project is in the design phase. The plan is to install 1,910 linear feet of sidewalks, 18 residential and 2 commercial driveway entrances, 850 linear feet of grading, and make some adjustments to residential irrigation. A total of 10 ADA ramps are needed on both the north and south sides of the street. 

Pavement treatment will also be completed to restore a smooth driving surface when completed.​

Map of Project Area

Timeline

Design is underway with construction anticipated to begin in winter 2024.

Project Number: ST87750154

Project Contact: Jeff Herzhaft, 602-918-0211

jeff.herzhaft@phoenix.gov​

​East Encinas Lane from 19th Street going east

This project is in the design phase. The plan is to install 276 feet of sidewalks with associated roll curb and gutter. Four driveway entrances and one ADA curb ramp will be removed and replaced. 

Pavement treatment will also be completed to restore a smooth driving surface when completed.

Map of Project Area

Timeline

Design is underway with construction anticipated to begin in winter 2024​​​


Project Number: ST87750154

Project Contact: Jeff Herzhaft, 602-918-0211

jeff.herzhaft@phoenix.gov​





​​​5th Street from Cheery Lynn Road to Flower Street

Design five-foot attached sidewalks on both sides of 5th Street between Cheery Lynn Road and Flow​er Street. Where five-foot sidewalks are not possible due to limited right-of-way or obstructions, four-foot sidewalks are acceptable. Install two ADA curb ramps at 5th Street & Flower Street, two ADA curb ramps at the corners of 5th Street and Cheery Lynn Road. Reconstruct two alley entrances, one commercial driveway, and one residential driveway; relocate one street signpost. 

Pavement treatment will also be completed to restore a smooth driving surface when completed.​

Map of Project Area

Timeline

Design is underway with construction anticipated to begin in fall 2024.

Project Number: ST87750155

Project Contact: Jeff Herzhaft, 602-918-0211

jeff.herzhaft@phoenix.gov​



​West of 35th Avenue on Mariposa, Pierson and Elm

Design four-foot attached sidewalks and driveways on both sides of Mariposa Street, Pierson Street, and Elm Street between 35th Avenue ​and 575 feet west of 35th Avenue. Construct one ADA curb ramp at the southwest corner of 35th Avenue & Mariposa Street. Relocate one streetlight at 3507 West Elm Street. 

Pavement treatment will also be completed to restore a smooth driving surface when completed.​​ ​

Map of Project Area

Timeline

Design is underway with construction anticipated to begin in fall 2024.

Project Number: ST87750155

Project Contact: Jeff Herzhaft, 602-918-0211

jeff.herzhaft@phoenix.gov​





​Colter Street from I-17 east frontage road to 23rd Avenue

Design 5-foot attached sidewalks on the north side of Colter Street between the I-17 east frontage road and extending 735 feet to the east; on the south side of Colter Street between 23rd Avenue and extending 645 feet to the west. Where 5-foot sidewalks are not possible due to limited ROW or obstructions, 4-foot sidewalks are acceptable. Design 2 ADA curb ramps (NEC of Colter & I-17 frontage road, NWC of Colter & 23rd Avenue) 1 modified driveway-ADA ramp (SWC of Colter & 23rd Ave), 1 commercial driveway entrance on the north side of Colter Street, and 10 residential driveway entrances on the south side of Colter Street between 23rd Avenue and 645' west of 23rd Avenue, install one streetlight on the south side of Colter Street, relocate 3 fire hydrants on the north side. 

Pavement treatment will also be completed to restore a smooth driving surface when completed.​

Map of Project Area

Timeline

Design is underway with construction anticipated to begin in fall 2024​.

Project Number: ST87750155

Project Contact: Jeff Herzhaft, 602-918-0211

jeff.herzhaft@phoenix.gov​

Updated October 2023


Street Transportation Title VI and ADA Program
Title VI Notice to the Public and ADA Policy Statement

The City of Phoenix Street Transportation Department hereby gives notice that it is the agency's policy to assure full compliance with Title VI of the Civil Rights Act of 1964, Title II of The Americans with Disabilities Act (ADA) and related statutes and regulations in all program​​​​​​​s and activities. These federal statutes require that no person shall, on the grounds of race, color, or national origin, be excluded from the participation in, be denied the benefits of, or be otherwise subjected to discrimination under any program, activity or service the City of Phoenix Street Transportation Department administers. More information regarding the Title VI program can be found at Street Transportation Title VI and ADA Program or email  STR Title VI Program.​​