Central Avenue Lane Reconfiguration and Parking Expansion Washington Street to Monroe Street

The Street Transportation Department has been asked to explore adding public metered parking on Central Avenue from Washington Street to Monroe Street.

The project would add 17 metered spaces to the east side of Central Avenue and result in the removal of one travel lane, reconfiguring three travel lanes into two. This would impact about 750 feet of Central Avenue. 

Project Highlights

  • Project perimeter: Central Avenue, from Washington Street to Monroe Street - about 750 feet of space
  • Proposal to remove one (1) northbound travel lane and add 17 metered parking spaces on the east side of Central Avenue
Graphic showing current lane configuration, which depicts three lanes of travel and no metered parking.
Current lane configuration.
Planned changes
Public Meeting (Youtube Banner) - CentralAveMap1

Project Timeline

  • Public meeting: July 14, 2026
  • Public Input Timeframe: July 14 to July 24, 2026
  • Seal Coat and Striping: Early August to mid-September 2026
  • Meter installation: Late September 2026

Community Engagement

The planning team held a virtual community meeting on Tuesday, July 14, 2026, to share proposed plans, and invite public input. Community input on this project is currently open until July 24, 2026.