Permitting Time Frames

​Share this page​

​​

  

Applications for the following permits are subject to Permitting (Licensing) Time Frames (State Law A.R.S.  9-835), which limits the number of business days the City of Phoenix has to review your project. The Permitting (Licensing) Time Frames are summarized in the table below.
 

Users of the City of Phoenix Sanitary Sewer

Permit Ty​​pe

Administrative Completeness Review

Substantive Review

Overall Time Frame

Discharge Request Form

3

7

10

New Wastewater Discharge Permit - Simple

30

60

90

New Wastewater Discharge Permit - Complex

45

135

180

Renewed Wastewater Discharge Permit

30

60

90

Alternative designs, installations, or operational features to a Wastewater Discharge Permit (see Note 4)

-

10 (see Note 4)

 

NOTES:

1. Definitions

The terms "Licensing" (Permitting) and "Working Day" are defined in State Law A.R.S. 9-831. These are the number of days (business days excluding Sat, Sun, and all legal holidays) that the City of Phoenix has to process the application and come to a final decision following receipt by the appropriate Section within the Environmental Services Division. The counting of days may be stopped to request additional information from the applicant.

2. Information Request  Mutual Agreement Application.

State Law A.R.S.  9-835(G) allows the City of Phoenix and the applicant to mutually agree in writing to allow the City of Phoenix to submit supplemental requests for additional information. The substantive review time frame and the overall time frame will be suspended from the date the request is issued until the date the City of Phoenix receives the additional information from the applicant. The Information Request - Mutual Agreement Application is a voluntary agreement designed to allow flexibility in the permitting (licensing) process and to avoid unnecessary delays, fees, and/or denial of the application due to unforeseen or unavoidable circumstances.

3. Time Frame Extension Mutual Agreement Application.

State Law A.R.S.  9-835(H) allows the City of Phoenix and the applicant to mutually agree in writing to extend the substantive review time frame and the overall time frame of a permitting (licensing) process by up to 25% of the overall time frame. The Time Frame Extension - Mutual Agreement Application is a voluntary agreement designed to allow flexibility in the permitting (licensing) process and to avoid unnecessary delays, fees, and/or denial of the application due to unforeseen or unavoidable circumstances.

4. Alternative Requests.

Each request for an alternative design, installation, or operational feature adds ten (10) business days to the substantive review time-frame.

5. 3rd Review Denial.

Applications found to be incomplete following the third (3rd) Administrative and/or Substantive Review will be denied for permitting (licensing) and required to reapply.

6. No Action Denial - Incomplete Application.

Applications returned for incompleteness following Administrative and/or Substantive Review must be completed and resubmitted within the time frame specified. No action by an applicant within 45-days of a returned application will result in denial for permitting (licensing).

7. Licensing time frames for Construction Permits.

Licensing time frames for Construction Permits necessary for the installation of Pretreatment Devices and Compliance Sampling Point Vaults are published and maintained by the City of Phoenix Planning​ Development Department.

8. Preemption.

To the extent that compliance with the licensing time frame provisions in A.R.S.  9-831 through 9-840 conflicts with the requirements of the federal Clean Water Act, 33 U.S.C. 1251 et seq., the federal Pretreatment Program regulations, 40 C.F.R. Part 403, or permits issued to and by the City pursuant to that authority, the requirements of the federal law or permit are presumed to control.